Our primary offer is to supply, or more commonly, supply and erect our kits to your site. The following outlines the different stages and our fee structure. You will be guided through this process by an architect who will be assigned to manage your project and be your primary point of contact. You can download a typical project programme from the brochures tab in our Members Area.
In order for us to release drawings based on your requirements, a deposit invoice of $1,250 will issued to you along with a Release Letter.
This letter outlines the terms and conditions of the project regarding use of th drawings for the house you have preliminarily chosen. It explains the services included at this stage of the project, before you have decided on which type of contract you would like to proceed with.
Please refer to the copyright details within the letter which outlines the terms and conditions of using a HebHomes designed kit house. It explains that you cannot use our designs to be built by another kit company. If you have any questions about this, please do not hesitate to ask for clarification from us.
Deposit: $1,250
We work with you to discuss the HebHome you wish and any changes that might be required to suit the site or other specific requirements. We will then produce schematic and design drawings for the HebHome which will be necessary for you or your agent to to submit to the relevant authorities for permit and planning approvals.
At this stage we will prepare an estimate for your kit cost depending on your house type and supply you with an order form which forms our Supply or Supply and Erect Contract. You will receive the following:
• Cover Letter
• Supply/ Supply & Erect Contract
• Specification of the Kit
Once these documents are signed and payment received, we will release the drawings for permitting
Kit Invoice Stage 1: 10% of kit estimate.
You would then appoint an agent or architect to undertake work to secure the planning and permit approvals for your home. We have associate architects who we can recommend to undertake this work.
Once you have received your relevant planning and permit approvals, we will then prepare detailed drawings and specification of the kit to allow the building contractors and kit manufacturers to customise the kit to your specific requirements and site.
We can them move onto the procurement of the kit.
Depending on how quickly you want to start on site, you will instruct us to proceed with the manufacture of the kit when you have a start date on site. At this point, we finalise your kit price and estimate the additional expenses, which includes delivery accommodation, telehandler/crane, subsistence etc. Once this is agreed, we appoint your kit supplier and order the windows on your instruction. You will be advised at this stage if there is a change to the provisional contract price.
Kit Invoice Stage 2: 30% of kit estimate.
A few weeks before the kit is due on site, we will ask for a written instruction to begin cutting the kit.
Kit Invoice Stage 3: 40% on 21 days before kit delivery
(Supply only: 60% on 21 days before kit delivery)
We will deliver the kit to your site to suit your contractor’s schedule. We will check beforehand that the site is suitable and ready for our erection team (if booked). Weather delays and extra costs associated with late delivery are borne by yourselves or your main contractor. The site prelims required to undertake the erection will be organised by your main contractor, including scaffold, welfare facilities etc.
Kit Invoice Stage 4: 15% on delivery of kit
After erection of the kit, the house is wind and watertight but there can still be water penetration so we would recommend proceeding with cladding and roofing as soon as possible. The windows are adjusted at the final stage of the erection process. After we have completed the erection, the final balance of our invoice will be issued. At completion of kit erection our supplier will provide a handover document to you or your agent to sign off on the build.
Kit Invoice Stage 5: 5% on completion of erection of kit
If you experience any problems with your windows or doors after the erection of the kit, please contact us detailing the issues you are experiencing, along with photos and videos. This will be then be passed onto the window supplier and your kit installer (if applicable) who will aim to have a response to you within 5 working days.